Six decisions. A better-prepared timber build.

Protect the design. Prepare more in the workshop. A practical guide to the six choices that connect drawings, manufacture and assembly.

Prefabrication makes early decisions work harder. Once the team agrees the details, Bächi Holzbau can turn them into prepared elements in the workshop — ready to arrive in the right order and fit into the building.

This guide follows the same six topics as the Technical Advisory drawing. Each explains why the decision matters, what to coordinate and the benefit of resolving it before production. The wall, floor, roof, concrete, window, façade and service connections all have their place within these six topics.

Decision 01 / 06

Structural system & build-up

A slim floor edge, a quiet room and a clear ceiling line all depend on the same build-up. Choosing the structure on its own can leave insulation, acoustics or services competing for space later. Bring these needs together while the section can still be shaped around the architecture.

Agree before production

  • Wall–floor junction: agree bearing, floor levels and ceiling lines together.
  • Allocate the layers for structure, fire resistance, acoustics and insulation.
  • Reserve service space before fixing the total depth.

Bring together: Architect, structural engineer, timber team and building-physics specialists.

What you gain

The proportions you designed, with room for the performance the building needs.

Decision 02 / 06

Openings & spans

A generous opening brings daylight and views. It also changes how loads travel through the wall and how the element can be handled. Developing the opening, support and window detail together keeps that architectural benefit achievable without a late change to the layout.

Agree before production

  • Confirm spans, supports and the stiffness around the opening.
  • Window junction: set the frame position, reveal, sill and installation allowance.
  • Align the opening schedule with the production drawing and window supplier.

Bring together: Architect, structural engineer, window supplier and timber team.

What you gain

Keep the light and views you want, with the opening ready to manufacture and fit.

Decision 03 / 06

Services & penetrations

The best route for a pipe or duct is usually the one planned before the timber is cut. Early coordination lets the workshop prepare the right opening and keeps services from disrupting structure, sound insulation or a visible ceiling later.

Agree before production

  • Locate service penetrations, with sizes and reference dimensions.
  • Agree fire-stopping, acoustic sealing and airtight connections where required.
  • Name who installs each seal and preserve access for installation and maintenance.

Bring together: Services planners, timber team and the relevant fire or acoustic specialists.

What you gain

Prepared routes and openings, with fewer improvised cuts or changes on site.

Decision 04 / 06

Interfaces

A building works when one package connects cleanly to the next. Treat the base, roof edge and façade as one coordinated envelope, rather than three separate trade details. Agree how the layers connect and who completes them before the next trade takes over.

Agree before production

  • Timber–concrete: agree reference levels, fixings, tolerances and moisture separation.
  • Wall–roof: connect insulation, airtightness and weather protection; allow installation access.
  • Façade: coordinate supports, movement, fixings and window, roof and base junctions.

Bring together: Architect, structural engineer, timber team, façade/roofing trades and building physicist.

What you gain

Adjoining trades build from the same detail, with fewer gaps in scope or sequence.

Decision 05 / 06

Visible timber

Exposed timber is both structure and finish. Joint positions, fixings and service routes become part of the room you see. Agreeing the intended appearance early allows production and assembly to protect the design, instead of trying to recover it at the end.

Agree before production

  • Exposed timber ceiling: set joint layout, visible fixings and service positions.
  • Agree timber species, surface quality and the intended finish, using a sample where useful.
  • Coordinate acoustic/fire requirements and protection during transport and assembly.

Bring together: Architect, timber team, services planners and relevant specialists.

What you gain

The timber character you chose, carried through to the finished room.

Decision 06 / 06

Fabrication & logistics

A well-designed element must also reach its place in the building. Transport, lifting, access and temporary support influence element size and the order of work. Resolve them alongside the design so the advantages of prefabrication translate into a smooth assembly.

Agree before production

  • Check element dimensions and weight against transport routes and crane capacity.
  • Agree delivery order, unloading space and what the site must have ready.
  • Plan temporary bracing, weather protection and handover to following trades.

Bring together: Timber production and assembly teams, site management and transport/lifting partners.

What you gain

More work arrives ready. Assembly follows an agreed sequence, with fewer decisions left on site.

Settle it once.
Put it to work in the workshop.

These questions belong to every well-planned building. Timber prefabrication gives the answers an immediate purpose: they shape the elements before they reach site. Start with the topics that could change geometry, build-ups or assembly. Record the agreed drawing, the responsible person and the next decision.

Bring Bächi Holzbau the plan or detail you want to develop. We connect the architectural idea with practical production knowledge and agree the next step with you.

Planning guidance. Project-specific design and specialist checks are agreed with the responsible project team.